Resources8 min read

AI in construction: Ontario is adding data centres faster than the grid can connect them

Ontario's data centres have the money committed. The grid decides when they get built.

AI at workOperations

Search for AI in construction and most of what comes up is software for estimating, scheduling and site safety. This page covers the other side: the buildings AI runs in. Ontario is putting up a lot of them, and each one needs a full electrical, cooling and mechanical build.

Ontario's pipeline is large and funded

The Toronto market had 479 MWSource 1 of data-centre capacity operating at mid-2026, with 248 MW under construction and another 372 MW planned. Beyond that, Canada's National Observer counted at least 15 proposed projects across Ontario totalling 2,202 MW.Source 2

The money is committed. Microsoft has pledged CAD 19 billionSource 5 for Canadian cloud and AI infrastructure between 2023 and 2027, and HIVE's BUZZ HPC has announced a CAD 3.5 billion facilitySource 7 in the GTA. Microsoft's Ontario expansion alone is expected to support 1,000 construction jobsSource 6.

Power sets the pace

The IESO, which runs Ontario's grid, reports about 7,000 MWSource 10 of data-centre connection requests, double the March figure. Any load over 10 MW needs two separate impact assessmentsSource 12, which can take more than a year. A site can be funded, designed and awarded to a general contractor and still be waiting on its connection.

The projects on record

Sizes are as published. Where a developer has not disclosed one, we say so.

ProjectMunicipalitySizeStageDeveloper or tenant
Toronto market, all operatorsGTA479 MW operating, 248 MW under constructionSource 1Mid-202648 operators
YTO11Vaughan48 MWSource 2,Source 4Near-operational, April 2026Microsoft
YTO12, 6100 Langstaff RdVaughanNot disclosedSource 3Pre-construction, EllisDon as general contractorMicrosoft
Markham facilityMarkham27 MWSource 1Delivered H1 2026, fully preleasedYondr
Hyperscale program, two sitesSouthern Ontario48 MW each, third site 57.6 MWSource 8Under construction, third site in pre-constructionConfidential cloud and AI provider, EllisDon as general contractor
AI facility, 9th LineOakvilleAbout 320 MWSource 1,Source 7,Source 17Proposed, target online H2 2027BUZZ HPC (HIVE)
Proposed campusMilton720 MWSource 2Proposed, no application filedLogistics Land Investments (TPA Group)
Proposed facilityNapanee250 MWSource 2ProposedUndisclosed
Industrial parkHamilton180 MWSource 2ProposedUndisclosed
Two facilitiesCambridge90 MW combinedSource 2UpcomingUndisclosed

Numbers refer to the sources below.

These projects buy whole power and cooling plants

EllisDon's published spec for one 48 MW facility calls for 21 generatorsSource 8 totalling 60.75 MW and 15,700 tons of cooling. Scopes on projects like these include:

  • Medium-voltage distribution, substations and transformers
  • Switchgear and electrical power monitoring
  • Standby generation, fuel systems and paralleling gear
  • UPS and battery rooms
  • Chilled-water plants, heat rejection and closed-loop cooling
  • CRAH and CRAC units, plus in-row and liquid cooling at higher densities
  • Building automation and controls
  • Process piping
  • Commissioning through integrated systems testing

Equipment prices have climbed. Cushman & Wakefield reports switchgear up 60% since 2021, generators up 33%, cooling equipment up 32% and transformers up 29%, against 7% for general construction materials.Source 1 Ontario's August 2026 framework expects closed-loop cooling and asks data centres to pay all their own energy costs.Source 10

The grid decides the schedule

Bill 40, in force since December 2025, lets the province prioritize which data centres connect.Source 12 The IESO's technical requirements for large computational loads went out as a draft on May 1, 2026 and reached version 3.0 on September 3.Source 13 Oakville has passed a one-year moratorium on new data centres.Source 10

The province expects data centres to make up 13% of new electricity demand by 2035Source 11, and the IESO forecasts data-centre demand rising from 3 TWh in 2026 to 16 TWh in 2050Source 9. For trades, that means start dates on these jobs can move with connection approvals.

General contractors check what they can verify fast

On mission-critical work, general contractors build their trade shortlists from what they can confirm quickly:

  • Your mission-critical projects by name, with scope, size and a general contractor or owner who will confirm them
  • Safety record: COR certification, WSIB clearance and recent incident rates
  • Commissioning experience through integrated systems testing, and the people who did it
  • Licences and factory training on the specified generators, UPS, switchgear and chillers
  • Bonding capacity, crew availability for the schedule, and 24/7 emergency response once the site is live

We go through each of these, and where it belongs, in What general contractors check before shortlisting a trade contractor.

Treat the loudest number as a bull case

Blackstone's Jon Gray told investors in September 2026 that new turbine orders now wait until 2030 or 2031.Source 16 Blackstone invests in data centres and power, so read that as an interested party's view. GE Vernova itself cites lead times of about three yearsSource 15 and a gas equipment backlog, including slot reservations, of 116 GWSource 14.

Why we mapped this

We put this together as part of our research into how GTA infrastructure trades run the office side of the build: bid invitations, prequalification packages, and the technical questions that land on estimators. We update it as projects move. If you work on this build and something here is out of date, write to us at hello@simplevision.ai.

FAQs

What readers usually ask

How many data centres are being built in Ontario?

At mid-2026, 248 MW of data-centre capacity was under construction in the Toronto market, on top of 479 MW already operating. Across the province, Canada's National Observer counted at least 15 proposed projects totalling 2,202 MW. Proposed is an early stage: the largest, a 720 MW campus in Milton, has no application filed.

Why do data centres need IESO approval to connect?

A large new load changes how the grid behaves, so it gets studied before it connects. In Ontario, any load over 10 MW needs a System Impact Assessment from the IESO and a Connection Impact Assessment from the transmitter, and together they can take more than a year. Since December 2025, Bill 40 also lets the province decide which data centres connect first.

What trades work on data centres?

Electrical, mechanical and controls trades all carry large scopes. Electrical work covers medium-voltage distribution, substations, transformers, switchgear, standby generators, UPS and battery rooms. Mechanical work covers chilled-water plants, heat rejection, closed-loop and liquid cooling, CRAH and CRAC units, and process piping. Building automation and commissioning through integrated systems testing run across both.

Will AI replace electricians?

No. AI runs in buildings that electricians wire and power, and every data centre needs people to install, terminate and commission that gear. Microsoft's Ontario expansion alone is expected to support 1,000 construction jobs. Where AI can help a contractor is in the office, with estimating and paperwork.

By SimpleVision, a Toronto practice built on 10+ years of product marketing and strategy for brands like Google, Apple, and Walmart. About the practice → We write with AI and check every figure against its source. How we write →

Sources 17
  1. 1Cushman & Wakefield, Americas Data Center Update H1 2026, Toronto pages 43 to 44 and cost page 5
  2. 2Canada's National Observer, "One data centre or one million homes? Mapping Ontario's proposed hyperscaler boom," March 2, 2026
  3. 3UrbanToronto, YTO12 Data Centre project record
  4. 4York Link, "Microsoft's near-operational Vaughan data centre unveiled," April 13, 2026
  5. 5Microsoft, "Microsoft deepens its commitment to Canada with landmark $19B AI investment," December 9, 2025
  6. 6Invest Ontario, Microsoft AI infrastructure expansion, April 7, 2026
  7. 7HIVE Digital Technologies, "BUZZ HPC announces 320 MW sovereign AI infrastructure in Greater Toronto Area," May 18, 2026
  8. 8EllisDon, Hyperscale Data Center Program
  9. 9IESO, 2025 Annual Planning Outlook, section 2.4.2.1, April 2025
  10. 10Daily Commercial News, "New data centres will pay all energy costs, get no cash incentives under Ontario plan," August 13, 2026
  11. 11Government of Ontario, "Ontario's Energy Plan Unlocking Opportunities in the Digital Economy," July 2, 2025
  12. 12BLG, "Data centre regulation in Ontario: Grid access rules," July 8, 2026
  13. 13IESO, Technical Requirements for Large Computational Loads Connecting to the Ontario Power System
  14. 14GE Vernova, Q2 2026 results release, July 22, 2026
  15. 15Power Engineering, "Data centers drive record surge in GE Vernova power equipment orders," April 23, 2026
  16. 16Blackstone, "Where's the Beef?" Jon Gray, September 2026
  17. 17UrbanToronto, BUZZ HPC Data Centre project record (3480 Ninth Line, Oakville)

Where this leads

Build the systems that run your business.

Custom AI that takes the busywork off your plate and runs in the background, so you get time back and revenue moving.

Start an auditBuilt to give you hours back every week